Cost-Plus-Incentive-Fee contract problem ---- Need Help-----
Submitted by Nik on Sat, 11/13/2010 - 05:34
Forums:
Hi All,
I have a doubt about the Cost Plus Incentive Fee contract problem mentioned below.
A project is contracted as a Cost-Plus-Incentive-Fee (CPIF) type of contract. The project is negotiated such that if the final costs are less than expected costs, the sharing formula for cost savings is 80:20. The targeted cost is US$ 500,000 with a 10% fee. If the project comes in at US$ 450,000, what would be the cost of the total contract
------------------------------------------------------