Need Help on a question
Submitted by nidhitripathi on Thu, 08/04/2011 - 18:55
Forums:
You are the project manager for Software Development project. The feasibility
study can start any time and takes 1 week and Requirement gathering takes
2 weeks which can start only after feasibility study. The Design and Test
Plan development can start in parallel after the Requirements gathering.
Test plan preparation takes 8 weeks followed by a review by the customer
and the time estimated for review is 1 week. After the review, Test Data
preparation takes 6 weeks.