Question
Submitted by sumedha82 on Sun, 08/21/2011 - 23:48
Forums:
A project is closed when the:
A) Client accepts the product
B) Lessons learned are completed
C) Archives are completed
D) Contract is finished
My answer is C and so is the correct answer. However, Rita P. 131 says that Index and archiving occurs first and lessons learned are updated after that
Pls clarify. Thanks