Questions on CPIF
Submitted by sumedha82 on Wed, 09/14/2011 - 13:35
Forums:
Hi Guys,
Can someone explain when to add target profit and when we do not. For eg. in below question. We did not add target profit.
The contract is a CPIF contract. Target costs= $ 500,000 ; Traget profit=$ 80,000. However, project was completed at $450,000. The incentive split is 80/20. How much is the total contract cost?
1) 470,000