n NPV
Submitted by arindammaiti on Fri, 09/23/2011 - 17:18
Forums:
A project would be executed over a span of 2 years. The cash flows are as follows: Year 1: -$2m, Year 2: $2.8m. Assuming a discount rate of 50%, should the project be selected?
Should be project be selected.
I chose yes.