PERT
Submitted by sammyyeung09 on Thu, 03/22/2012 - 05:11
Forums:
You are appointed the project manager of a proposed natural gas treatment plant. You are expected to deliver this project. Construction site has been acquired without land survey. It is required to construct a temporary office at the project site before the main project begins. The activities and duration in days are as follows:
A- prepare foundation (7days)
