Plan Risk Response - updates to Project management plan without change approval
Hi,
I am trying to understand the Plan risk response process, here I find that, since risk response actions/strategies, Project management plan/subsidiery plans are updated. My questions are since this is a change to already approved baselines why these response actions are not performed through change/Perform integraded change control. If my understanding is wrong, please corrrect me. One more thing PMBOK says Response actions are impemented in Monitor and control process (Not in Excecution process???)
Thanks,
kghebbar