Float versus standard deviation

Question: The sponsor wants the project to be completed in 40 days. The CPI is 1.1, the project critical path duration is 38 days with the standard deviation of 2 days. What is the maximum project float.


a) 8 days


b) 2 days


c) 4 days


d) 0 days


The answer is 4.


Can anyone explain what is the relation ship between float and standard deviation.


Thanks,


Abdul khadar


 