Float versus standard deviation
Submitted by shaikfromriyadh on Sun, 04/29/2012 - 12:50
Forums:
Question: The sponsor wants the project to be completed in 40 days. The CPI is 1.1, the project critical path duration is 38 days with the standard deviation of 2 days. What is the maximum project float.
a) 8 days
b) 2 days
c) 4 days
d) 0 days
The answer is 4.
Can anyone explain what is the relation ship between float and standard deviation.
Thanks,
Abdul khadar