On the site mentioned by you I again visited and did PSM or Project Scope Management this time.
On question 6, the question is on the outputs of Collect Requirements. I saw Requirements Management Plan and Reuirements Documentation both as options. I was surprised since both are outputs. Anyway, I marked Requirements Documentation and the answer came as wrong as the answer should be RMP.