Confused with this cost Question
Submitted by RaviDatt on Sun, 07/08/2012 - 21:53
Forums:
Question from Rita Fast Track.
Halfway through the exeuting processes of your project, a team member alerts you to a potential cost overrun for a specific deliverable. What do you do FIRST
A Determine the projected actual cost.
B implement a change control.
C Inform the customer.
D Determine the cause of the overage.
Answer is D but I am not convienced how? My explaination.