Difference between M&C and Verify Scope

You are measuring the dimensions of a highly critical component in your project that was manufactured by one of your subcontractors. Failure of this component is a huge risk factor and would lead to major delays  and possibly a failed project. In which process group does this activity belong ?

1. Project risk management

2. Monitoring and controlling

3. Verify Scope

4. Executing