Need Some expert advice on CPI and SPI interprettation
Submitted by Anonymous (not verified) on Tue, 11/13/2012 - 23:55
Forums:
I had a question in OL 175.
Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?92
o The project was terminated early. At that time, it was over budget and ahead of schedule.
o The project has produced additional deliverables which were originally not required.
o The project has evidently been finished under budget and behind of schedule.
o The project has evidently been finished over budget and ahead of schedule.