Need Some expert advice on CPI and SPI interprettation

 I had a question in OL 175.

Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?92

o The project was terminated early. At that time, it was over budget and ahead of schedule.

o The project has produced additional deliverables which were originally not required.

o The project has evidently been finished under budget and behind of schedule.

o The project has evidently been finished over budget and ahead of schedule.

 