Weird Earned Value Question
Submitted by YogSam on Mon, 02/02/2015 - 03:43
Forums:
Question : If the Cost Variance is negative and the SPI is smaller than one, what does this indicate?
A.) Your project is ahead of budget but behind schedule
B.) Your project is ahead of budget but on schedule
C.) Your project is behind budget and ahead of schedule
D.) Your project is behind budget and behind schedule
What should be the correct answer ?
I know its behind schedule but what is 'Ahead of Budget' and 'Behind Budget' ?