Urgent help - exam day after tomorrow - thx
Submitted by genone on Tue, 03/08/2011 - 09:19
Forums:
Got exam day after tomorrow - will appreciate your help. Thanks.
Are risks with probability greater than 70% called Issues??
Sample question below says Answer is B with reason as -- "any risk that is >= 70% is not a risk any more, it is an issue. They should be entered into the issues"