Question on Calculation of communication channels - Please help with solution
1. You are managing a telecom project. You have got two teams reporting to you. One team is responsible for equipment installation and the other team is responsible to commission and test that equipment. Both teams are working in parallel such that as soon as the installation teams finishes equipment installation at one site they move on to another site for installations and the commissioning and testing team start their activities on the newly installed site.