Please help answer this question as PMPBOY is stumped...

Question (from CheetahLearning):   Who should be held accountable for ensuring the program delivers
on the delivery date that was initially approved?


A.  Project Managers
B.  Change Control Board (CCB)
C.  Program Team
D.  Program Manager


Correct answer is B.  Can someone please explain how correct answer should be B?