EAC question
Submitted by working_hard on Tue, 08/23/2011 - 03:00
Forums:
I understand that we should this formula to calculate EAC when variances are typical
EAC = AC + [(BAC-EV) / CPI]
When should we use the following formula?
EAC = AC + [ (BAC-EV) / (CPI * SPI) ]
Thanks in advance.