Submitted by Patta on Fri, 08/26/2011 - 19:46
Forums:
Hi,
Can somebody please tell me what should be the right answer. I thought it be 4. What do you say???/
In your new project, you have to provide a critical deliverable within five months and do not have time to go through the Conduct Procurements process. You decide to sign a contract with a supplier with whom your company has done some work in the past. The risk you are accepting in this situation is: