Closing question
Submitted by pmasp1 on Fri, 12/02/2011 - 02:06
Forums:
Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8
and an SPI of 1.25. What is a plausible explanation for that?
o The project was terminated early. At that time, it was over budget and ahead
of schedule.
o The project has produced additional deliverables which were originally not
required.
o The project has evidently been finished under budget and behind of schedule.
o The project has evidently been finished over budget and ahead of schedule.