PMP Q on verify scope.
The client responds back that the deliverables do not match the requirements and need to be reworked. The client emphasized that there are medium severity defects in the system which were clearly mandated in the requirements as "should not exist" in the final deliverables. The project manager is not sure if this was communicated but after looking at the Project Management Plan and the Requirements Documents, he confirms that this was not communicated.