Answer is?
Submitted by krantikumar50 on Mon, 06/25/2012 - 11:50
Forums:
Hi All, SS, and respected Pawarji Sir,
Please answer this and probably with the expalnation:
A. You are a project manager of a project. You have organized a meeting to plan risk management. Who could be attendees for this meeting?
1.Stakeholders
2.Team members
3.anyone in organization who is responsible to manage risk planning
4.All of the above