Please help - Rough order of magnitude question (ROM)
Submitted by Anonymous (not verified) on Mon, 07/02/2012 - 05:25
Forums:
You are working for FALCON highway construction agency as a project cost estimator. The agency started a highway construction project which is in it's planning phase. The rough order of magnitude (ROM) cost estimate for the project is expected to be between 3 and 5 million dollars in the planning phase with a ROM of -25% to +25%. What will be the ROM estimate in the execution phase if it changes to -10% to +10%?