A question about free float
Submitted by aliweb on Mon, 07/09/2012 - 16:51
Forums:
Ok I have made the following question for you guys.
Considering the following network diagram in which Activity A will take 7 days, Activity G 6 days and Activity F 13 days, what is the free float on Activity C?
A. Free float cannot be calcuated because information provided is not complete
B. There is no free float on Activity C
C. The free float on activity C is 13
D. The free float on activity C is 7