Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator:

------------------------------

Your Risk Register says if your IT Administrator is unavailable for a period longer than a week it will cause serious issues for your project. You have just learned from you Human Resource Department that your IT Administrator has resigned and has given a one-month notice for the company to find a replacement.
This situation is an example of which of the following:

A.) Secondary Risk
B.) Residual Risk
C.) Contingency Plan
D.) Trigger