PERT Question - Need Help
Submitted by Nader on Tue, 09/18/2012 - 12:25
Forums:
Dear All,
I have found an interesting question, but I'm facing some trouble getting an answer. Please check below:
Thanx in advance ...
The project manager for a project is going to use the PERT method of scheduling for the project that she is working on.
Using PERT calculation the variance for the project is found to be 25 days.