Free PMP Exam Sample Question
Submitted by pmpodcast on Mon, 10/08/2012 - 07:35
Forums:
The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------
An element of a Work Breakdown Structure that can be viewed at the lowest level of each branch is referred to as which of the following?
A.) Control Account
B.) Work Breakdown Structure Component
C.) Work Package
D.) Task
------------------------------
Hint: A work package is at the lowest level of a WBS.
------------------------------