Critical path question
Submitted by boumbo on Sun, 10/14/2012 - 14:13
Forums:
Question:-
start 0
C Start 3
D C 6
A C 8
E D 4
B A,E 5
F E 3
End B,F 0
if B duration gets changed to 3, what is the effect on proje?
A - the project will complete sooner if F starts immediately?