Free PMP Exam Sample Question
Submitted by pmpodcast on Tue, 11/13/2012 - 00:59
Forums:
The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------
Which of the following Enterprise Environmental Factors does not influence the Estimate Activity Durations process?
A.) Duration Estimating Databases
B.) Project Management Information Systems
C.) Productivity Metrics
D.) Published Commercial Information
------------------------------