An activit has an ES of 3 days, LS of 13 days, EF of 9 days and LF of 19 days.
What is the duration of the activity?
A. 3
B. 6
C. 7
D. 10
Could someone kindly explain it? as i found some different calcution and thus result in wrong ans.