3 Questions
Many more changes were made to the project during the project executing process than had been expected. What is the best thing for the project manager to do now?
1. Wait until all changes are known, print and revise the baseline
2. Make changes as needed , but maintain a schedule baseline
3. Make only changes approved by the management
4. Talk to management before any changes are made
What is the best technique to ensure project work is really complete?
1. Final performance reporting
2. Procurement audits
