project performance SV
Submitted by nitsbaba on Mon, 01/21/2013 - 16:42
Forums:
while reviewing the project performance, the project manager determines that the SV = -500.
what is the best thing to do?
1- let sponsor know
2- determine CV
3- look for activities that can be done in parallel
4- move resources from the project to one that is not failing
can someone suggest what approach to follow while handling these type of questions