Total Float & Free Float Question ?
Submitted by rjbuzzing on Fri, 01/25/2013 - 21:28
Forums:
In a project, an activity on the critical path has been delayed by 5 days. when you revist the project schedule,you find that another activity with 5 days free float and third activity with 10 days total float. Assuming similar resources are required for all the activities in the project , what should be done?