All of the following situations will cause schedule activity duration estimates to directly influence the cost estimates except:
a) When the project budget includes cost of financing components
b) when planned components and control accounts are not adequately defined in the WBS
c) When seasonal cost variations are involved
d) When union labor with regularly expiring collective bargaining agreements are involved