The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------
You planned for Contingency Reserves for your office building construction project and used contingency plans to control risks. However, your attempts to control project risks were not effective. What is the next step you should take?
A.) Use a Fallback Plan.
B.) Escalate to the project team.
C.) Perform the Plan Risk Responses process again.