Free PMP Exam Sample Question
The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------
You are using Microsoft Project as a tool to manage the project. All the activities have been recorded and the Work Breakdown Structure has been prepared. Your project team wants to use different units of work for different resources. Which document establishes the information regarding units of measurement for resources on a project?
A.) Enterprise Environmental Factors
B.) Cost Management Plan
C.) Project Charter