Question related to Close Process - PMP
Submitted by hemald on Thu, 08/06/2015 - 07:48
Forums:
Hello
Please let me know the correct choice for the following:-
When should administrative closure be carried out?
A At the completion of each phase of the project
B At the completion of project
C At the completion of each deliverable
D At the completion of each procurement contract on the project
The sample test says A is correct.
Please help, since I am not able to understand it.
Thanks