Standard Deviation
Can somebody explain the following question please?
A project manager has been asked by the client to meet the promise date of the project. The project manager analyzes the schedule before promising a date to the customer. The project manager uses the program evaluation and review technique to evaluate the project schedule. She decides that based on the PERT calculations she can promise a delivery date of June 30. The expected value of the project completion date is May 30. If the project manager is willing to accept a 5% probability that the project will be delivered later than June 30, what is the standard deviation of the duration of the activities on the critical path? Assume a five-day workweek.
a. Ten days
b. Fifteen days
c. One-half month
d. One month


sspawar
Fri, 08/03/2012 - 15:29
Permalink
As per 3point estimate
As per 3point estimate (PERT - wieghted average beta distribution method)
ans will be 15 days
refer earlier Question
http://www.pmzilla.com/mock-questions
http://er-sspawar.blogspot.in/
MuhammadKhan74
Fri, 08/03/2012 - 16:05
Permalink
Thanks a lot. Regards, MK
Thanks a lot.
Regards,
MK
sspawar
Sun, 08/05/2012 - 03:12
Permalink
THIS ARTICLE MAY HELP A LOT
THIS ARTICLE MAY HELP A LOT -from -
http://www.interventions.org/pertcpm.html
5.2. Probability of Project Completion by Due Date
Now, although the project is estimated to be completed within 28 weeks (te=28) our Project Director would like to know what is the probability that the project might be completed within 25 weeks (i.e. Due Date or D=25).
For this calculation, we use the formula for calculating Z, the number of standard deviations that D is away from te.
By looking at the following extract from a standard normal table, we see that the probability associated with a Z of -0.6 is 0.274. This means that the chance of the project being completed within 25 weeks, instead of the expected 28 weeks is about 2 out of 7. Not very encouraging.
On the other hand, the probability that the project will be completed within 33 weeks is calculated as follows:
The probability associated with Z= +1 is 0.84134. This is a strong probability, and indicates that the odds are 16 to 3 that the project will be completed by the due date.
If the probability of an event is p, the odds for its occurrence are a to b, where:
Select Bibliography
sspawar
Sun, 08/05/2012 - 13:06
Permalink
Most of the places I saw that
Most of the places I saw that this question is wrongly answered as option C =45 days(one and half month), without any justification.
I saw a blog in PMHUB, and many other sites , all are just copying , as 45 days without knowing the reasons why.
Some of them are little adding it with 95 % probability (appx) of 2sigma and thus of normal distribution but still they are answering 1.50month.
If It is by 2sigma of NDC, then one sigma = 31/2= 15days appx, also answer comes B. But it is wrong approach.
at here 95 % is different then
what
shown in NDC figure
see 47.87 (LHS)+47.87(RHS) = 95.73 %
where as in question it is
50(LHS) + 45 (RHS) = 95%
it makes a great difference
47.87-45 = 2.87%
with this difference at ends (flattered curve) = 45will give 1.65SIGMA, (value of Z, in Z score curve), while 47.87 will give = 2sigma.
-------------------------------------------------------------------------------------------------------
It can be checked in Excel program also
There is one formula NORMINV ( prob %age in decimal, MEAN DATE, SD) will give END date (pessimestic date).
But in this question given M = a Mean date, Prob %age = 95% and End date and asking SD =?
Could not be solved , directly.
But by indirect , by GOAL seek function of Excel =
Putting in formula NORMINV (0.95,30th May,SD) = 30th of June, by goal seek will give SD = 18.80 days( it also works on Normal Distribution Curve theory)
-----------------------------------------------------------------------------------------------------------------------------------------
BY PERT formula SD = P-O/6, Beta distribution , weighted average, method
Assuming -3sigma as Optimistic values = 3*31/1.645= 54 days, and pessimistic as cutoff date at 95% prob = 31 days from mean
= p-o/6 = 85/6 =14.1 appx = 15 days.
--------------------------------------------------------------------------------------------------------------------------
By no other way answer will come.
pmalik
Sat, 12/03/2016 - 12:09
Permalink
PERT & SD
The ans would be 15 days.
For complete explanation on PERT and SD, you can read following articles
* PERT Formula and Use of Standard Deviation
* How to use PERT, CPM and Standard Deviation Together?