SPI before task should start?
Submitted by twinkler on Fri, 08/12/2011 - 11:56
How to calculate EV, CPI and SPI for this example?
- assume task or project has BAC = 1000
- planned start (PS) of a task or project is in the future
- therefore the PV = 0
- teams did not wait until they are allowed to start and have already performed 75% of the work
- AC = 300
Forums:


admin
Sat, 08/13/2011 - 07:04
Permalink
I guess we will have to
I guess we will have to calculate EV for future date assuming PV > 0. What is the exact question ?