SPI
Submitted by vijayavadrevu on Mon, 06/03/2013 - 14:40
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, but the actual work completed is 20% of the total work. What is Schedule Performance Index (SPI) in this case?
A)1.66
B)1
C)2.5
D)1.9
Forums:
MANOJ RAMRAOJI ...
Mon, 06/03/2013 - 16:00
Permalink
A
EV= (Total Cost / total project months) * total months completed = ($240,000 / 12) * 4 = $80,000
PV = Total Cost *percentage actually completed = $240,000 * 20 / 100 = $48,000
SPI = $80,000 / $48,000 = 1.66
Regards,
Manoj
DonJuanin
Mon, 06/03/2013 - 18:14
Permalink
Hi Manoj,Your calculation
Hi Manoj,
Your calculation makes sense however my question is how you came to conclusion that total months completed are 4? Question mentioned "The project is now in the fourth month, but the actual work completed is 20% of the total work."
Can you please explain?
Thanks
cnppmp
Mon, 06/03/2013 - 17:41
Permalink
SPI=1.66
BAC=240,000
PV= 4/12 * 240,000=80,000
EV=20% of 240000= 480000
SPI= EV/ PV= 80000/ 48000
= 1.66
Regards
CN Patil
vijayavadrevu
Mon, 06/03/2013 - 17:44
Permalink
Yes, Patil. It's correct
Yes, Patil. It's correct
DonJuanin
Mon, 06/03/2013 - 18:17
Permalink
PV= 80000EV = 48000SPI =
PV= 80000
EV = 48000
SPI = EV/PV
= 48000/80000
This is not equal to 1.66, SPI should be below 1.
hema
Tue, 06/04/2013 - 07:50
Permalink
SPI
@Patil
As per your calculation PV = 80000 and EV = 48000
SPI = EV/PV = 48000/80000 = 0.6
But the answer is not in the list? Could you please explain
cnppmp
Mon, 06/03/2013 - 18:24
Permalink
Vijaya Please make sure you
Vijaya
Please make sure you udnerstand the basic concepts of the EV, PV, AC, BAC. If you have these in the question or you have to derive one of them the sufficient information would be provided in it.
For example, consider the above question.
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, but the actual work completed is 20% of the total work. What is Schedule Performance Index (SPI) in this case?
Regards
CN Patil
vijayavadrevu
Tue, 06/04/2013 - 04:00
Permalink
Thank You very much
Thank You very much Mr.Patil, for the piece of advise. I'll definitely keep in mind
sandeshkd
Tue, 06/04/2013 - 02:16
Permalink
Am I missing something?
PV at the end of 4 months = $240,000*(4/12) = $80,000
EV at the end of 4 months = 20% of $240,000 = $48,000
SPI = EV/PV = 48,000/80,000 = 0.6
This is not listed in the options, am I missing something here, can someone please clarify.
subinoyd
Tue, 06/04/2013 - 02:25
Permalink
EV = BAC * 20% = 48000PV =
EV = BAC * 20% = 48000
PV = 4/12 * 240,000 = 80,000
SPI = EV/PV = 48000/80000 = 0.6
The question does not have this option. But this shall be the correct answer according to me. Would appreciate if the admin can contribute with opinion.
Regards,
Subinoy
pmpnewster
Tue, 06/04/2013 - 03:17
Permalink
How can the SPI for the given project be greater than 1?
How can the SPI for the given project be greater than 1? From the given data, it is clear that the project is behind schedule.
Also, the question says that the project is NOW in the 4th month. I would interpret the question as meaning that the project has now entered the 4th month and hence would go for 3 months completed (and not 4). Regardless of this choice, the SPI would be less than 1.
Vijaya, can you please tell us the officially provided explanation for this question? Thanks.
Regards.
vijayavadrevu
Tue, 06/04/2013 - 04:13
Permalink
@pmpnewsterThis is the
@pmpnewster
This is the explanation provided "Schedule Performance Index (SPI) = Earn Value / Planned Value Earn Value = (Total Cost / total project months) * total months completed = ($240,000 / 12) * 4 = $80,000 Planned Value = Total Cost *percentage actually completed = $240,000 * 20 / 100 = $48,000 SPI = $80,000 / $48,000 = 1.66"
the reason why I have posted this question is
1) I too have taken the time as 3 months instead of 4 months and found no option available
2)Then I have started working with 4 months. Even then, in the explanation given, Planned Value = Total Cost *percentage actually completed
PV = BAC * % planned and EV = BAC * % actually completed (as per my understanding)
hence posted this question
Regards
Vijaya
kalpesh242
Fri, 12/11/2015 - 16:59
Permalink
EV - % work actually
EV - % work actually completed * Project budget
= 0.2 * 240,000 = 48,000 means EV = 48,000
PV = Budgeted cost of work scheduled
scheduled is 4 month
PV = 20,000 * 4 month = 80,000
SPI = EV/PV = 48,000 / 80,000 = 0.6
But this option not available.
Since work is behind schedule anyway 1.66 is not correct.
Any comment ? agreement ? I am confused as I saw this in practice test.