Simple Question

 Need Help - It seems very straight forward question but answe make me confuse.

Q:  You, as the project manager, are planning to document relevant information on interest, involvement, and impact of the stakeholders on the project success. Which of the following communication processes should you follow? 

  Choice 1 Stakeholder analysis
 
  Choice 2 Plan communications
 
  Choice 3 Manage Stakeholder expectations
 
  Choice 4 Identify Stakeholders
 
Also I want to understand that if
 
" We are planning to document relevant information on interest, involvement, and impact of the stakeholders " 
 
What process we are in?
 
Thanks -

Documentation of relevant information on interest, involvement, and impact of the stakeholders is done in Identify stakeholder process. So Answer would be D: Identify Stakeholders. PMBOK 249

 You are right -  But what confused me is the impact of the stakeholders  - Isnt it done as a part of Stakeholder analysis?

 

 Stakeholder Analysis is not a process, it is a tool!! 

Hope this clears your doubt

 Got it - 

Thanks alot ----