Sequencing method
Submitted by san on Thu, 04/25/2013 - 04:53
Jack is working with his project team to develop a network diagram, and noticed that a series of activities can go in parallel but must end in a specific sequence. What type of activity sequencing method should be used?
Answers :
1)Precedence diagramming method
2)Arrow diagramming method
3)Critical path method
4)All of the above
Which one to choose between 2 and 3
Forums:


Jgrind07
Thu, 04/25/2013 - 05:08
Permalink
Option 1 - Precedence
Option 1 - Precedence diagramming method
Precedence diagramming method - A schedule network diagramming technique in which schedule activities are represented by boxes (or nodes). Schedule activities are graphically linked by one or more logical relationship to show the sequence in which the activites are to be performed. PMBOK 4 Page No:441
Arrow diagramming method used in PMBOK 3 and obviously the critical path activities need not be in the order of sequence of activities like A-B-C-D.
Thanks
Jai
sathya737
Thu, 04/25/2013 - 05:34
Permalink
sequencing method
Hi
PMBOK 4, does not speak about Arrow diagramming method,the answer shall be either 1 or 3 but agian PDM is used in critical path methodology so the answer shall be 3.
Sathya
sspawar
Thu, 04/25/2013 - 05:40
Permalink
ans will be D not relevant
ans will be D
not relevant to pmbok 4
crushPMP
Thu, 04/25/2013 - 14:15
Permalink
There are so many bad
There are so many bad outdated sources out there, that I am more concerned of falling into such traps than about the actual exam.
admin
Fri, 04/26/2013 - 05:36
Permalink
That is why you should take
That is why you should take mock exam only from reputed sources, else you will be wasting lot of time and get confused.