Sequencing method

  
Jack is working with his project team to develop a network diagram, and noticed that a series of activities can go in parallel but must end in a specific sequence. What type of activity sequencing method should be used?
Answers :  
 1)Precedence diagramming method
 2)Arrow diagramming method
 3)Critical path method
 4)All of the above

Which one to choose between 2 and 3

Option 1 -  Precedence diagramming method

Precedence diagramming method - A schedule network diagramming technique in which schedule activities are represented by boxes (or nodes). Schedule activities are graphically linked by one or more logical relationship to show the sequence in which the activites are to be performed. PMBOK 4 Page No:441

Arrow diagramming method used in PMBOK 3 and obviously the critical path activities need not be in the order of sequence of activities like A-B-C-D.

 

Thanks

Jai 

Hi


PMBOK 4, does not speak about Arrow diagramming method,the answer shall be either 1 or 3 but agian PDM is used in critical path methodology so the answer shall be 3.


Sathya

 ans will be D 

not relevant to pmbok 4

crushPMP's picture

There are so many bad outdated sources out there, that I am more concerned of falling into such traps than about the actual exam.

admin's picture

 That is why you should take mock exam only from reputed sources, else you will be wasting lot of time and get confused.