PMBOK page: 312 - The implementation of a contingency plan or workaround sometimes results in a change request.
Does this mean that implementing a contingency plan will not result in a secondary risk?
Forums:


admin
Mon, 08/08/2011 - 11:39
Permalink
No, it does not say that.
No, it does not say that. Implementing contingency plans may result in secondary risks.
kghebbar
Mon, 04/09/2012 - 04:46
Permalink
It may or may not result in
It may or may not result in secondary risk alos, if these implentation of contingency plan or workaround impacts project objectives, cost/chedule base lines, then it should be a change request and must undergo change process.