Scope baseline question
Submitted by ba1980 on Mon, 07/08/2013 - 16:50
| Question : | While preparing the scope baseline who should be involved? |
| Answers : | |
| Functional managers | |
| Project Team | |
| Stakeholders | |
| Project expediter |
Project team or Stakeholders?
Forums:


elthox
Mon, 07/08/2013 - 17:08
Permalink
Scope Baseline is created
Scope Baseline is created during Create WBS in which all the Project team must be involved.
ba1980
Mon, 07/08/2013 - 17:14
Permalink
Agreed WBS is created with
Agreed WBS is created with help of Project team.
But scope statement which is part of scope baseline is created with inputs from all stakeholders. Collect requirements is done with help of Stakeholders.
humanbeing2001
Mon, 07/08/2013 - 17:58
Permalink
For PMI, at every nuke and
For PMI, at every nuke and corner activity Stakeholders' involvement is paramount.
But while palnning Scope Baseline, WBS & Work packages are formed and Project team involvement becomes necessary to have ownership over work packages.
Hence the answer is Project Team
bkthakkar
Tue, 07/09/2013 - 05:01
Permalink
Yes, Project Team
Yes, Project Team