1. Project Finance committment is ........in the beggining
a. Higher
b. Unchanged
c. Lower
2. Fundamental requirement from a member in team is....
a. Cooperation and Trust
b. Share information and organizational policies
3. The people working in another country comes across a religious day. The one of team member ask for leave. PM should
a. Grant Leave
b. Grant leave ask to compensate later
4. Feasibility Analysis results in
a. Project Charter
b. Project Scope Statement
5. TO encourage others for PMP is.....responsibility
a. Social
b.Ethical
c.Professional
d. Obligation
6. Most difficult job for PM to know in Overseas projects is
a. Custom
b.Culture
c.Laws
7. Work performed per time
a. Task
b. Package
8. Sponsor Cut funding for project, then first thing project manager do would
a. Negotiate contingency plan
b. Negotiate Scope
c. Negotiate schedule
9. If there is some savings the decision shall be made in Favour of
a. Customer
b. Sponsor
10. PM should select people based on
a. Willingness and availability
b. Standard of performance
11. If a certain activity need some time say 4 days
we geenrally move time from activity having float of 4 days or from activity having zero float but over all project float of 8 days
Apologies if some questions are not clear
bishop
Thanks in advance


pradeepsodha
Sun, 08/16/2009 - 06:15
Permalink
Sample questions
Hi All,
My answers are highlighted. The questions are very short and un-common.
Please comment.
1. Project Finance committment is ........in the beggining
a. Higher
b. Unchanged
c. Lower
2. Fundamental requirement from a member in team is....
a. Cooperation and Trust
b. Share information and organizational policies
3. The people working in another country comes across a religious day. The one of team member ask for leave. PM should
a. Grant Leave
b. Grant leave ask to compensate later
4. Feasibility Analysis results in
a. Project Charter
b. Project Scope Statement
5. TO encourage others for PMP is.....responsibility
a. Social
b.Ethical
c.Professional
d. Obligation
6. Most difficult job for PM to know in Overseas projects is
a. Custom
b.Culture
c.Laws
7. Work performed per time
a. Task (Q not clear)
b. Package
8. Sponsor Cut funding for project, then first thing project manager do would
a. Negotiate contingency plan
b. Negotiate Scope
c. Negotiate schedule
9. If there is some savings the decision shall be made in Favour of
a. Customer
b. Sponsor
10. PM should select people based on
a. Willingness and availability
b. Standard of performance
11. If a certain activity need some time say 4 days
we geenrally move time from activity having float of 4 days or from activity having zero float but over all project float of 8 days
???