Sally is a project manager working on a project that will require a specially engineered machine. Only three manufacturers can make the machine to the specifications Sally needs. The price of this machine is particularly critical to this project. The budget is limited, and there's no chance of securing additional funds if the bids for the machine come in higher than budgeted. She's developing the source selection criteria for the bidders' responses and knows all of the following are true except for which one?

Sally will use understanding of need and warranties as two of the criteria for evaluation.

Sally will review the scope baseline, teaming agreements, and risk register as some of the inputs to this process.

Sally will base the source selection criteria on price alone since the budget is a constraint.

Sally will document a SOW, the desired form of response, and any required contractual provisions in the RFP

Sally will base the source selection criteria on price alone since the budget is a constraint.