Risk Register
Submitted by sai_murthy on Mon, 08/02/2010 - 01:55
Want to understand , is there any specific reason, why the "Risk Register is not shown as an INPUT for Develop Schedule process to add any schedule contingenicies reserves"
Forums:


vejandla
Fri, 08/06/2010 - 17:38
Permalink
Required for Cost
In triple constraint (scope, time, cost), the Risk Register is not required for both scope & time. It's required for "cost" contriant only. Why only Cost? Well, you want to consider risks (threats & opportunities) while doing the cost estimates and according to PMBOK not required while defining Scope & Schedule.
Any other insight would be helpful also.
Thanks