A project manager has just finished the risk response plan for a US$387,000 engineering project. Which of the following should he probably do NEXT?
a) Determine the overall risk rating for the project.
b) Begin to analyze the risks that show up in project drawings
c) Add work packages to the project work breakdown structure
d) Hold a project risk reassessment

vishwanathkanchipmp's picture

a) Determine the overall risk rating for the project.

Regards,

Kanchi

 

 

I think option "A" is the right answer.

 

Answer should be C. See the Rita's process chart. After risk management it is go back iteration