A project manager has just finished the risk response plan for a US$387,000 engineering project. Which of the following should he probably do NEXT?
a) Determine the overall risk rating for the project.
b) Begin to analyze the risks that show up in project drawings
c) Add work packages to the project work breakdown structure
d) Hold a project risk reassessment
Forums:


vishwanathkanchipmp
Tue, 08/25/2015 - 12:51
Permalink
a) Determine the overall risk rating for the project.
a) Determine the overall risk rating for the project.
Regards,
Kanchi
thiru26@gmail.com
Tue, 08/25/2015 - 17:06
Permalink
Option "A"
I think option "A" is the right answer.
riyerashwin
Wed, 08/26/2015 - 05:40
Permalink
Answer should be C. See the
Answer should be C. See the Rita's process chart. After risk management it is go back iteration