 In your project, you are about to complete Plan Risk Responses process. Completion of certain tasks marks the end of the process. Which one from the following is NOT that task?

 
 
A- People have been identified to take responsibility for each agreed-to and funded risk response.
 
B-High priority risks are addressed in detail in the risk register.
 
 C-Low priority risks are included in the risk mitigation plan if they occur.
 
 D-Negative risks have been considered for avoidance, transference or mitigation.
 

C looks the most appropriate answer due to:

1) Low Priority risk which are included in watchlist are an output of Qualitative Risk Analysis.

2. If you talk about big projects where you have several hundreds of risk, generally you dont waste time on preparing a respone for low priority risks, they are usually kept in a watchlist and monitored.

C
Refer pmbok low priority risk are not considered in risk response and these are kept in watch list