Right Answer

Which one is right option from the following - 

1. Monte Carlo analysis is a very effective maunal analysis.

2. Crtical path can include a dummy activity.

3. Only one crtical path can exist in any project.

4.Fast tracking is better than crashing.

 

By looking choice and using elimination technique, i got the right anser - which is 2. However, can someone help me understanding what is dummy activity means here. 

Thanks,

Trish

 it seems old  stuff.

 in AOA method it is there.

as per pmbok 4, this method is now obsolete and never be asked

see

http://pmzilla.com/are-these-typical-pmbok-4th

CP may have dummy activity

see

http://www.cpmtutor.com/c05/fp-dummies.html