Which one is right option from the following -
1. Monte Carlo analysis is a very effective maunal analysis.
2. Crtical path can include a dummy activity.
3. Only one crtical path can exist in any project.
4.Fast tracking is better than crashing.
By looking choice and using elimination technique, i got the right anser - which is 2. However, can someone help me understanding what is dummy activity means here.
Thanks,
Trish
Forums:


sspawar
Sun, 04/28/2013 - 10:01
Permalink
it seems old stuff. in AOA
it seems old stuff.
in AOA method it is there.
as per pmbok 4, this method is now obsolete and never be asked
see
http://pmzilla.com/are-these-typical-pmbok-4th
CP may have dummy activity
see
http://www.cpmtutor.com/c05/fp-dummies.html