A project team with CPI of 0.78 is looking for options to reduce cost. Which of the following should be the BEST option to choose in this scenario?
A)Reduce a test cycle, in the System Testing phase
B)Reduce scope by cutting down non- essential features
C)Add more resources to expedite the schedule
D)Revisit estimates and eliminate risks
Forums:


crushPMP
Mon, 05/06/2013 - 16:42
Permalink
Can't be A, B or C. So i'll
Can't be A, B or C. So i'll go with D.
A - Can't just randomly cut a testing cycle - Quality should not be compromised.
B - Reduce Scope - Definitely No
C - Adding more resources, increases cost - aka Crashing.
vijayavadrevu
Mon, 05/06/2013 - 17:05
Permalink
You are right. Answer is
You are right. Answer is given as D
Jgrind07
Mon, 05/06/2013 - 20:50
Permalink
I choose D as it is the only
I choose D as it is the only applicable choice eventhough I'm not sure if revisitng estimates will reduce cost. If you revist estimate (here I think the estimate should be reduced), you may have to compromise with quality or scope or something else..
Thanks
Jai